Construction waste diversion rate calculator

Enter your scale-ticket tonnage by material stream to calculate construction waste diversion and estimated points under both LEED v4.1 and LEED v5. Use it during preconstruction or mid-build to see whether source-separated roll-offs or a certified commingled processor will clear the 50% or 75% credit threshold.

  • Calculator
  • Updated November 3, 2026
  • Sources: USGBC
Sorted and baled recyclable materials
Photo: City of Greenville, North Carolina, public domain.
  • WeightsTons by stream
  • Methodsv4.1 and v5
  • PointsA planning estimate

Estimate your diversion rate

Weights by stream, from your scale tickets

Leave out excavated soil, land clearing debris and hazardous waste. Both LEED versions exclude them. Rows you leave blank are ignored.

0%diverted, v4.1 methodof 0 tons total

Material streams diverted
0
Estimated v4.1 points
0 of 2
v5 effective diversion
0%
Share salvaged or source separated
0%
Estimated v5 points
0 of 2
Mixed debris rate used
0%

A planning estimate only. The rating system and reference guide decide the credit, and your LEED team submits it. See the LEED construction waste credit guide.

How it works

How LEED v4.1 and LEED v5 score waste diversion

Both rating systems count weight from haul tickets, though LEED v5 rewards source separation and salvage far more than commingled sorting.12

VersionHow diversion is countedPoints
LEED v4.1Diverted weight divided by total project waste. Reach 50% across at least two material streams (1 point), or 75% across at least three streams (2 points), or use a certified commingled facility path1 or 2
LEED v5Source-separated recycling counts 100%, salvaged or reused material counts 200%, and commingled debris counts at the processor's recovery rate (capped at 35% unless third-party verified). Alternative daily cover and incineration count as disposal. At least 10% of diverted tons must be salvaged or source separated at the 50% tier, and at least 25% at the 75% tier1 or 2

Leave excavated soil, land-clearing debris and hazardous waste out of every input, since both LEED versions exclude them from total construction waste. This tool models the standard diversion-rate, stream-count and separated-share thresholds; it does not model total-waste-per-square-foot reduction paths or certified commingled facility exemptions.

Running a LEED jobsite?

We stage source-separated and commingled roll-offs, collect facility recovery documentation, and deliver monthly tonnage reports backed by scale tickets.

Using the result

How to move a borderline diversion rate

Where jobsites typically gain or lose a point mid-build.

  1. 01

    Sitting below 50%?

    Check your landfill tonnage first. Pulling one heavy stream out of general trash, especially clean concrete, scrap metal or framing lumber, moves total weight percentage fastest.

  2. 02

    Diverting enough tons, still short a point?

    Verify stream counts under v4.1 (two streams at 50%, three at 75%) and source-separated or salvaged share under v5 (10% at 50%, 25% at 75%). Commingled hauls alone cannot earn v5 points without that separated share.

  3. 03

    Relying on commingled C&D sorting?

    Under LEED v5, unverified processor recovery rates cap out at 35%. Request current third-party verification paperwork from the sorting facility before sending mixed loads there.

  4. 04

    Keep scale tickets current

    Credit submittals require haul-by-haul weight documentation matched to each receiving facility. Collect tickets monthly rather than chasing haulers at substantial completion.

Common questions

Diversion rate questions

How is the diversion rate calculated?

Under LEED v4.1, divide total diverted weight by total non-hazardous construction and demolition waste. Under LEED v5, source-separated recycling counts at 100% of weight, salvaged material counts at 200%, and mixed C&D counts at the processing facility's recovery rate (capped at 35% unless third-party verified).

What counts as diverted?

Materials sent off site for recycling, salvage or reuse. Alternative daily cover (ADC) and waste-to-energy incineration count as landfill disposal in both versions, except clean wood converted to fuel where permitted under LEED v4.1.

Should I include soil in the calculator?

No. Both LEED v4.1 and LEED v5 exclude excavated soil, rock, land-clearing debris and hazardous waste from construction waste calculations.

What if I do not know the mixed debris recycling rate?

Leave the percentage field blank so the calculator treats mixed debris conservatively at 0% diverted until you get facility documentation. Under LEED v5, any facility rate without third-party verification is capped at 35%.

Is this the official LEED calculation?

No. This calculator is a preconstruction and mid-job planning tool built from published USGBC rating-system rules. Your LEED consultant submits official documentation using USGBC templates and the reference guide.

Can you provide the weights?

Yes. When we manage your project's roll-offs, we track tonnage by material stream and compile scale tickets into monthly diversion reports. Call sales at (888) 588-2607 to set up a jobsite.

Ticket-backed diversion reporting across every haul

We coordinate local haulers and recyclers under one contract, compile scale tickets by material stream, and send one consolidated invoice. If a swap is missed, we escalate with dispatch the same business day.

Read next

Sources

  1. U.S. Green Building Council, LEED v4.1 Building Design and Construction rating system, MR credit Construction and Demolition Waste Management. Checked November 3, 2026. usgbc.org
  2. U.S. Green Building Council, LEED v5 Building Design and Construction rating system, July 2026, MRc5 Construction and Demolition Waste Diversion. Checked November 3, 2026. usgbc.org