General conditions site services template

Temporary site services live in Division 01 general conditions rather than trade subcontracts: office trailers, perimeter fence, portable toilets, generators, roll-off hauls, concrete washout, and final clean. Leaving out winter heat fuel, crane-lifted high-rise toilets, or two months of punch-list demurrage eats straight into project fee. Download our free three-page PDF and Word worksheet to scope quantities, phase durations, and bid assumptions before locking your GMP.

  • Free template
  • Updated November 3, 2026
  • Sources: eCFR
A construction site with trailers, fencing and containers
Photo: Florian Haider, Unsplash License.
  • Line itemsEvery service listed
  • PhasesWhen each is on site
  • AssumptionsWhat to confirm

Why it matters

Code minimums and project phasing drive the quantities

Estimating Division 01 site services as a flat percentage of construction value misses federal safety ratios, stormwater permit mandates, and seasonal runtime spikes.

LineWhat drives the quantity
ToiletsPeak daily trade headcount under OSHA Table D-1: minimum 1 unit for 20 or fewer workers, 1 toilet seat and 1 urinal per 40 workers up to 199, and 1 seat and 1 urinal per 50 workers at 200+1
LightingNight shifts, winter start hours, and OSHA Table D-3 minimums: 5 foot-candles across general construction areas and 30 foot-candles in field offices and first-aid stations2
Washout and containersConcrete pour volume and stormwater permit containment rules for washout slurry and covered dumpsters; see SWPPP site services
Waste and recyclingExpected haul count by phase, source-separated LEED streams, and heavy-debris weight caps; see construction recycling
Power, heat and coolingUtility temp-pole lead times, trailer compound kVA draw, and winter curing or drywall-drying fuel burn; see temporary power and heating and cooling

Putting numbers to your Division 01 estimate?

Send over your completed worksheet or project schedule. We source vetted local providers for every temporary service line and return one itemized quote.

The template

What is in the PDF

Three letter size pages. The PDF has fields you can type into, and the Word version opens in any editor. Use the preview to see the layout first.

Page 1: project and facilities

Project details, then trailers, storage, fence, toilets, hand wash and drinking water.

UseFill in at the start

Page 2: power, waste and safety

Power, light and climate, waste and recycling, and safety, traffic and cleaning lines.

UseAdd quotes as they arrive

Page 3: schedule and assumptions

When each service is on site by phase, and the assumptions to confirm before you lock the budget.

UseUpdate with the schedule

Common questions

General conditions questions

What are general conditions in construction?

General conditions are the temporary Division 01 facilities, utilities, equipment, and site support required to run a construction project that do not remain part of the finished structure, including office trailers, storage containers, perimeter fencing, portable toilets, temporary power and heat, dumpsters, and stormwater controls.

What site services should be in the budget?

Break temporary site services into four buckets: field facilities (trailers, conex boxes, fence, toilets, hand-wash stations, holding tanks, drinking water), temporary power and climate (generators, spider boxes, light towers, heaters, fuel), waste and recycling (roll-offs, trash chutes, concrete washout, diversion reports), and site controls (barricades, erosion control, wheel wash, dust suppression).

How many toilets do I need to budget for?

Size toilet counts against peak trade headcount by phase rather than project average. Under 29 CFR 1926.51 Table D-1, OSHA requires at least one toilet for 20 or fewer workers, one toilet seat and one urinal per 40 workers from 20 to 199, and one seat and one urinal per 50 workers at 200 or more, with weekly or multi-weekly pumping adjusted for crew load.

Does the schedule change the budget?

Directly. Perimeter fence, office trailers, and baseline sanitation mobilize on day one and stay through final punch list, so every month of schedule slip adds another billing cycle across almost every rental line, plus winter heat or generator fuel if utility energization slips.

Is the template editable?

Yes. Both a fillable three-page PDF and an editable Word file are linked above at no cost, ready to drop into your preconstruction estimate folder.

Can you price all the lines?

Yes. Send us your completed worksheet or mobilization schedule, and we will price and manage sanitation, roll-offs, fencing, storage, office trailers, temporary power, water, and fuel across local providers on one agreement. Call sales at (888) 588-2607.

Every site service on one quote

Local providers do the work; we hold the contract, own the problems, and send one bill. If a delivery gets missed, we contact the provider the same business day.

Read next

Sources

  1. 29 CFR 1926.51, Sanitation, Table D-1. Checked November 3, 2026. ecfr.gov
  2. 29 CFR 1926.56, Illumination, Table D-3. Checked November 3, 2026. ecfr.gov