Detritus/How many units

Planning guide

How many portable toilets do you actually need?

The regulatory minimum and the number that keeps a site working are not always the same. Here is what changes the count, along with examples from sites we have served.

By Zach Nespinsky, VP, Revenue Operations. Updated October 9, 2026.

The OSHA minimum is a headcount table

For construction, 29 CFR 1926.51, Table D-1, is the floor. Meet that count first. A long job often needs more units or more service than the table, because the table does not account for walking distance, peak weeks, or how often the units are pumped.

EmployeesMinimum toilet facilities
20 or fewer1 toilet
More than 201 toilet seat and 1 urinal per 40 workers
200 or more1 toilet seat and 1 urinal per 50 workers

The same section requires adequate washing facilities where employees handle paints, coatings, herbicides, insecticides, or other harmful contaminants, and those facilities have to be near the work. It does not publish a hand-wash-station ratio. On our orders the range is about one station per three restroom units to one per eight. A 130-person construction site used eight units and three stations.

Table D-1 also does not set an accessible-unit count. Where a permit or contract requires an accessible toilet, plan on at least one unless the authority has confirmed otherwise in writing. The 2010 ADA Standards govern facilities that have to follow them. They are not a crew-size formula.

Start with the floor, then plan above it

Meet the OSHA count, then account for how the site actually runs. A long project staffed to the bare minimum has a way of generating complaints by month three.

The operational number is driven by four things, in roughly this order of impact:

Examples from completed orders

These are setups we have delivered, with the customer's reported headcount where available. Use them as reference points, not a sizing formula.

SiteHeadcountWhat was deliveredImplied ratio
Construction site, commercial130 expected users8 standard units, 3 hand wash stations~1 unit per 16 people
Distribution warehouse, water outage250 peopleThree 10-stall restroom trailers, 3 hand wash stations~1 stall per 8 people
Small crew, long duration4 laborers, 6 monthsUnits with interior sinks, serviced twice weekly1 unit per 4, higher service
Sports club, year-longNot stated40 standard units, 5 hand wash stations8 units per station
Highway rest area, 12 monthsPublic4 standard plus 2 ADA units, weekly service1 in 3 units ADA
Park event, 45 days2,000 per daySix to eight stall trailers, weekly servicingSized on peak concurrency
Five-week theatre productionCast, crew, audience12 standard, 2 ADA, 2 portable sinks4 cleanings per week

Detritus order records. Headcounts are as reported by the customer at time of order. These are delivered configurations, not recommendations for your specific site.

More service can cost less than more units

If people are complaining about cleanliness rather than lines, another weekly service may help more than another unit — and usually costs less. These are schedules we currently run:

FrequencyTypical use
WeeklyStandard construction placement, moderate crew density
Twice weeklyHigh-density crews, hot climates, small unit counts
Three times weeklyAgricultural and multi-site operations with concentrated use
Four times weeklyExtended public-facing runs. We service a Monday, Wednesday, Friday and Sunday pattern on multi-week productions
Event-specificOvernight cleaning before a peak morning. On weekend tournaments we drop Friday and clean Saturday night for Sunday use

Two expensive sizing mistakes

These show up after mobilization, when the original quantity is already on the site.

Sizing to average, not peak

Crew count on a construction build is not flat. On one solar program monthly placements went from 4 to 90 within nine months. A fixed quantity set at mobilization was never going to last; without a scaling plan, the mismatch shows up as complaints instead of a change order.

Forgetting hand wash

Hand-wash stations are easy to miss, and inspectors tend not to miss them. They are a separate line item on nearly every provider's rate card, so make sure somebody asks.

Want it sized against your actual site?

Send peak crew count, duration, the site address, and whether the work is spread across a large parcel. We come back with a unit count, a service frequency, and pricing. If your headcount is going to move, say so and we will build the scaling in rather than pretending it is fixed.

Common questions

What does OSHA require for construction toilets?

Under 29 CFR 1926.51, Table D-1, a site needs one toilet for 20 or fewer employees, one toilet seat and one urinal per 40 workers above that, and one toilet seat and one urinal per 50 workers at 200 or more. That is the regulatory floor. A longer job often needs more service or more units than the table. The rule is published at osha.gov.

How many portable toilets do I need for 100 workers?

Start with the OSHA table, then consider the length of the job and service frequency. One hundred workers is above 20 and below 200, so Table D-1 calls for one toilet seat and one urinal per 40 workers. For longer projects, roughly one unit per 15 to 20 workers tends to hold up better than that floor. We supplied a 130-person construction site with eight standard units and three hand-wash stations, or about one unit per 16 people. Eight units serviced weekly and eight serviced twice weekly are not the same setup.

What is the ratio of hand wash stations to toilets?

OSHA's construction rule requires adequate washing facilities where crews handle contaminants. It does not set a station-to-toilet ratio. Our orders commonly range from one hand-wash station per three units to one per eight. A 130-person construction site used eight units and three stations; a sports club order included 40 units and five stations. Food service, healthcare, and other health-code-sensitive sites usually need the higher ratio, and inspectors do check.

How many units for an event?

Event planning is driven by peak concurrency and duration rather than total attendance, because everyone queues at the same time. A park event expecting 2,000 people per day across 45 days was scoped around six to eight stall trailers rather than individual units. Multi-day events also need a service schedule built around the peak, including overnight cleaning before the busiest morning. Wedding and festival counts are on the event planning guide.

Does service frequency change how many units I need?

Yes. On a long placement, adding service can be cheaper than adding units, especially when the complaint is cleanliness rather than availability. Our schedules range from weekly to four times a week. For one five-week production, that meant service on Monday, Wednesday, Friday, and Sunday.

Do I need ADA units?

The OSHA toilet table does not set an accessible-unit count. A contract or permit often still requires one. Our orders have included two ADA units in a 14-unit event order, two in a six-unit highway rest-area placement, and ADA-accessible trailers for a residential building. Assume you need at least one unless the relevant authority has confirmed otherwise in writing.